Leeville Viaduct Upgrade

This project involved the replacement of an existing 505 metre long viaduct structure over a floodplain located 10km south of Casino.

Features:

  • 3500 tonnes of precast concrete, comprising 135 individual spans
  • over 1200 precast concrete elements ranging from 0.5-0.9 tonnes, and
  • 6 hour windows to complete as many span replacements as possible.

Benefits:

  • Existing train service unaffected by construction work
  • Design solution that enabled all work to be undertaken during existing windows between trains, and
  • Minimal maintenance solution with a 100-year design life.

Client: Australian Rail Track Corporation (ARTC)

Leeville Viaduct Upgrade
You must install Adobe Flash player and enable Javascript in your browser in order to view this video.
Related Projects
  • CityRail Upgrade, New South Wales
  • Saudi Arabia North-South Railway Project
  • Sydney to Brisbane Rail Upgrade
  • Goonyella Electrification Project
  • TPI Trackwork and Bridges Alliance
  • Alice Springs to Darwin Railway
  • Hornsby Platform 5 and Stabling Project
  • Chatswood Transport Interchange
  • Leeville Viaduct Upgrade