Onslow Loadout Jetty

Western Australia

This project involved the construction of the Onslow Solar Saltfield minesite infrastructure, wash plant, materials handling system and jetty loadout.

FEATURES:

  • 1.4km long jetty, including design of piling works
  • loadout platform
  • 4 berthing dolphins, and
  • commissioning of conveyors and shiploader.

BENEFITS:

  • project completed 3 months early even though unseasonable weather interrupted work on 2 occasions
  • construction period over before the start of the main cyclone season, and
  • excellent safety record with no lost time injuries.

CLIENT: Onslow Solar Salt Pty Ltd

Prev Next