Blackwater, Queensland
This project was Australia's largest ever turnkey design and construct coal handling and preparation plant contract, undertaken in joint venture. The team provided a fully integrated multi-disciplined design with plant capacity to produce 14mtpa, replacing Blackwater Mine's existing North, South and Thermal plants.
FEATURES:
- receiving plant for Run of Mine coal
- crushing and screening plant
- 60,000t raw coal stockpile/blending bed
- two module 1,800tph wash plant
- 450,000t product coal stockpile
- two traveling, slewing, luffing stackers
- two portal reclaimers
- train-loading system to load 7,000t trains in 1.4 hours
- all civil work, structural, piping and mechanical works
- all high and low voltage electrical works
- instrumentation works
- plant control systems and operator controls
- commissioning of the total project.
BENEFITS:
- over 30 years coal mine infrastructure works experience, particularly in materials handling facilities
- application of current coal handling and processing technology reducing overall operating costs
- improvements in mine efficiency from the new generation plant, contributing significantly to the mine's long-term sustainability
- construction of the new plant allowed the decommissioning of the South Blackwater rail spur and loop, opening up access to significant reserves.
CLIENT: BHP Billiton Mitsubishi Alliance (BMA)